Currently on display:
Step 1: Select a project
Step 2: Pick a date, Graph will display a week's data, beginning the Monday of the week chosen
 
Step 3: Click the button to update

DateDaily Comments
5/5/2008 12:00:00 AM"Court Order: 100 kcfs/100 kcfs; 24-Hr Avg Spill = 99.1 kcfs TDG waiver not exceeded @ Cascade Island (12-hr Avg TDG = 117.7%); TDG @ Camas Washougal exceeded 115% (12-hr Avg TDG = 119.4%) *Camas Washougal TDG higher than Cascade Island*"
1234

Comment links correspond to the order of days in the week.

 
* Graph runs 7 days, Monday - Sunday.
Spill Season Update

 


 

In accordance with the Court Order, spill was initiated at the Snake River Projects at 0001 hours on April 3, 2008. The Court Order calls for the following spill levels at the Federal Snake River Projects:

Project Spring Spill (April 3 - June 20) Summer Spill (June 21 - August 31)
Day / Night Spill Day / Night Spill
Lower Granite 20 Kcfs / 20 Kcfs 18 Kcfs / 18 Kcfs
Little Goose 30% / 30% 30% / 30%
Lower Monumental Gas Cap / Gas Cap 17 Kcfs / 17 Kcfs
Ice Harbor 30% / 30% vs 45 Kcfs / Gas Cap 30% / 30% vs. 45 Kcfs / Gas Cap

Court ordered spill at the lower Columbia projects began on April 10, 2008. The Court Order calls for the following spill levels at the Federal Lower Columbia River Projects:

Project Spring Spill (April 10- June 30)* Summer Spill (July 1 - August 31)
Day / Night Spill Day / Night Spill
McNary 40% / 40% 40% / 40% vs. 60%/60% (beginning around June 15th)
John Day 0 / 60%; 30% / 30% vs. 40% / 40% study 30% / 30% vs. 40% / 40% study
The Dalles 40% / 40% 40% / 40%
Bonneville 100 Kcfs / 100 Kcfs

85 Kcfs / Gas Cap (June 21 - July 20)
75 Kcfs / Gas Cap (July 21 - Aug 31)

*MCN and BON beginning summer spill research prior to July 1 (see
dates in above table)

Court Order Spill:

All projects have a minimum powerhouse flow requirement:

Project Minimum Powerhouse Flow (kcfs)
Lower Granite 12
Little Goose 11.5
Lower Monumental 11.5
Ice Harbor 9.5 (Mar-Jul), 9 (Aug-Nov)
McNary 50
John Day 50
The Dalles 50
Bonneville 30

At low flows the Court Ordered spill amounts cannot always be provided along with minimum powerhouse flows (PH Min). In this instance all estimates of Court Order Spill (i.e., red line on graphs) are adjusted for project specific powerhouse minimum requirements using the following criteria:

If Total Flow > Court Order + PH Min ' Court Order = Court Order
If Total Flow < Court Order + PH Min ' Court Order = Total Flow - PH Min.

Spill to the Gas Cap:

In the Court Order, spill to the gas cap means to spill a volume of water that achieves the total dissolved gas (TDG) waivers, specifically, the 120% tailrace TDG criteria, and the downstream forebay 115% TDG criteria. To assess whether the Court Order is being implemented the spill should be evaluated relative to whether the 120% TDG is being met in the tailrace, and the 115% is being achieved at the next downstream forebay. Both TDG levels are plotted on the graph for each project.

The US Army Corps of Engineers (COE) develops daily levels of maximum spill that the COE estimates will not exceed the TDG criteria. The "spill caps" estimated by the COE are given to the project operators as maximum spill levels. The "spill caps" presented in the graphs are taken directly from the COE. These "spill caps" are updated by the COE every two weeks so the graphs may lag several days. The COE's assessment of meeting the Court Order is dependent on whether a project spills to the "spill caps".

LGS:
Court Order spill at LGS for spring 2008 is 30% of instantaneous flow for 24-hours a day. The Court Order calls for night-time spill to be provided to the gas cap for 14-days. The start date of this operation will be determined by FPAC and will be between April 22nd and May 15.

IHR:
IHR is conducting spill tests under two different levels of Court Order Spill (30%/30% versus 45 kcfs/Gas Cap). These different spill levels will be tested in 2 day blocks throughout spring and summer 2008.

MCN:
MCN will be testing to levels of Court Order spill for summer 2008 beginning around June 15th (40%/40% versus 60%/60%). These different spill levels will be tested in 2 day blocks throughout the summer spill season.

JDA:
JDA will be testing to levels of Court Order spill for spring and summer 2008, beginning around April 27th (30%/30% versus 40%/40%). These different spill levels will be tested in 2 day blocks throughout the spring and summer spill seasons.

Note: Spill at some projects varies relative to flow, therefore the scale of Y-axes may be different for each project and may change from week to week at an individual project.

Today is:

Copyright © 2000-2008 Fish Passage Center.