Currently on display:
Step 1: Select a project
Step 2: Pick a date, Graph will display a week's data, beginning the Monday of the week chosen
Step 3: Click the button to update

DateDaily Comments
8/29/2011 12:00:00 AM"Court Order: 75 Kcfs/Gas Cap; 24-hr Avg Flow = 160.1 Kcfs; 24-hr Avg Spill = 94.3 Kcfs; Cascade Island (12-hr Avg TDG = N/A) - TDG monitor malfunction; Camas/Washougal (12-hr Avg TDG = 112.7%) - Not a point of compliance for TDG waiver;"
123

Comment links correspond to the order of days in the week.

 
* Graph runs 7 days, Monday - Sunday.
Spill Season Update

 


 

In accordance with the Court Order and 2011 Spring Fish Operations Plan (FOP), voluntary spill was initiated at the Snake River Projects at 0001 hours on April 3, 2011. Summer spill volumes were initiated at 0001 hours on June 21, 2011, per the 2011 Summer FOP. The 2011 Spring and Summer Fish Operations Plans call for the following spill levels at the Federal Snake River Projects. 

Project

Spring Spill (April 3 - June 20)

Summer Spill (June 21 - August 31) –

Day / Night Spill

Day / Night Spill

Lower Granite

20 Kcfs / 20 Kcfs

18 Kcfs / 18 Kcfs

Little Goose

30% / 30%

30% / 30%

Lower Monumental**

Gas Cap / Gas Cap

17 Kcfs / 17 Kcfs

Ice Harbor

30% / 30% vs 45 Kcfs / Gas Cap

30% / 30% vs. 45 Kcfs / Gas Cap

In accordance with the Court Order and 2011 Spring FOP, voluntary spill was initiated at the Lower Columbia projects at 0001 hours on April 10, 2011.  Summer spill levels were initiated on the dates specified below for each project, per the 2011 Summer FOP. The 2011 Spring and Summer Fish Operations Plans calls for the following spill levels at the Federal Lower Columbia River Projects.

Project

Spring Spill (April 10- June 30)

Summer Spill (Through August 31, start dates below) –

Day / Night Spill

Day / Night Spill

McNary

40% / 40%

50% / 50%

(beginning June 20, 2011)

John Day

30% / 30% and

40% / 40%

30% / 30% and 40% / 40%

(beginning July 1, 2011)

The Dalles

40% / 40%

40% / 40%

(beginning July 1, 2011)

Bonneville

100 Kcfs / 100 Kcfs

85 Kcfs/121 Kcfs vs. 95 Kcfs/95 Kcfs (June 16 - July 20) and

75 Kcfs/Gas Cap (July 21 - August 31)

Court Order Spill:

All projects have a minimum powerhouse flow requirement. The table below provides the range of minimum powerhouse requirements for each project, followed by the assumed minimum for the graphs (in parentheses).  The assumed minimum requirements include project specific miscellaneous flows (e.g., adult fishways).

Project

Minimum Powerhouse Flow (kcfs)

Lower Granite

11.3-13.1 (12)

Little Goose

11.3-13.1 (12)

Lower Monumental

11.3-13.1 (12)

Ice Harbor

8.5-10.3 (10.5 Mar-Jul)

McNary

50-60 (55)

John Day

50-60 (51.2)

The Dalles

50-60 (56)

Bonneville

30-40 (42)

At low flows the Court Ordered spill amounts cannot always be provided along with minimum powerhouse flows (PH Min). In this instance all estimates of Court Order Spill (i.e., red line on graphs) are adjusted for assumed project specific powerhouse minimum requirements using the following criteria:

If Total Flow > Court Order + PH Min ' Court Order = Court Order
If Total Flow < Court Order + PH Min ' Court Order = Total Flow - PH Min.

12-hr Avg TDG:

The 12-hr average TDG levels that are presented in the graphs above are according to the Oregon method of calculation. This method of calculation estimates the 12-hr average TDG based on the 12 highest hourly TDG readings in a 24 hour period. These 12 highest hours are not necessarily consecutive.

**Spill to the Gas Cap:

In the Court Order, spill to the gas cap means to spill a volume of water that achieves the total dissolved gas (TDG) waivers, specifically, the 120% tailrace TDG criteria, and the downstream forebay 115% TDG criteria. To assess whether the Court Order is being implemented, spill should be evaluated relative to whether the 120% TDG is being met in the tailrace, and/or the 115% is being achieved at the next downstream forebay. Both TDG levels are plotted on the graph for each project.

The US Army Corps of Engineers (COE) develops daily levels of maximum spill that the COE estimates will not exceed the TDG criteria. These estimated "spill caps" are given to the project operators as maximum spill levels. The estimated "spill caps" presented in the graphs are taken directly from the TMT website (http://www.nwd-wc.usace.army.mil/tmt/documents/ops/spill/caps/).  However, updates of the estimated “spill caps” are not always available and, thus, the FPC graphs may lag several days. The COE's assessment of meeting the Court Order is dependent on whether a project spills to the estimated "spill caps".

IHR:
Spring and summer spill at IHR will alternate between two different levels of Court Order Spill (30%/30% versus 45 kcfs/Gas Cap).  Prior to April 28th, spill at IHR will be 45 Kcfs/Gas Cap.  From April 28th to July 13th, the two spill levels will be alternated in 2 day blocks. After July 13th, spill at IHR will be 45 Kcfs/Gas Cap

JDA:
JDA will be evaluating two levels of spill in spring and summer 2011, beginning around April 27th (30%/30% and 40%/40%).  Prior to the start of the testing, spill at JDA will be 30%/30%.  After the test is concluded on July 20th, spill at JDA will be 30%/30%.

Note: Spill at some projects varies relative to flow, therefore the scale of Y-axes may be different for each project and may change from week to week at an individual project.

[ Home ] [ Adult ] [ Smolt ] [ Spawning ] [ River ] [ Hatchery ] [ Documents ]

Today is:

Copyright © 2000-2010 Fish Passage Center.